1. Materials: Materials cost shall include:
(1) Direct material cost;
2. Material procurement: labor costs, transportation costs, handling costs, storage costs;
(3) material loss cost in the process of processing;
(4) Product anti-corrosion material cost
(5) Expenses of other auxiliary materials, etc.
2. Processing cost: Processing cost shall include:
(1) Labor cost of processing;
(2) processing machinery expenses;
③ The power cost of processing (such as water, electricity, etc.) ;
(4) Cost of processing auxiliary materials (such as electrode, welding wire, etc.).
3. Installation cost: The installation is generally carried out on site, and the cost shall include:
(1) On-site installation labor costs;
② transportation cost of finished products on the installation site;
(3) Safety and protection costs of finished products at the installation site;
(4) Water and electricity costs of on-site installation;
⑤ The cost of temporary facilities on the installation site.
4. Commissioning cost: Commissioning cost shall include:
(1) Commissioning costs (including cold weather water subsidy costs, etc.);
② Commissioning of water and electricity costs (partly paid by the owner);